New Wet Chemical Fire Suppression System Installation

VeePro Fire Protection Sdn. Bhd. completed the installation of a new wet chemical fire suppression system for a commercial kitchen. The system is specially designed to protect cooking equipment and hood areas where flammable oils pose a high fire risk. This installation ensures rapid suppression in the event of a grease fire, minimizing damage and downtime.

Wet chemical systems are essential for fast, targeted kitchen fire suppression. VeePro ensures every installation meets NFPA standards and BOMBA compliance.

The project involved pipework routing, nozzle placement, cylinder mounting, control unit setup, and fusible link installation. Our team tailored the system layout based on kitchen equipment and hood size to ensure maximum coverage. Post-installation testing and client training were also conducted to ensure proper understanding of how the system operates during a fire.

Project Features :-

Customized suppression system to protect kitchen operations and staff safety:-

How the Job Was Done :-

Efficient service execution carried out with professional tools and care:

Site Briefing & Layout Confirmation
We met with the site contact to confirm the final kitchen layout, type of cooking appliances used, and optimal nozzle positions for maximum fire coverage.
Cylinder & Pipe Installation
The wet chemical cylinder was mounted securely in an accessible area. Stainless steel pipework was routed through the kitchen hood system to all nozzle points, keeping aesthetics and safety in mind.
Nozzle, Link, and Pull Station Setup
Discharge nozzles were placed over key cooking equipment. Fusible links and manual pull stations were installed as part of the activation mechanism, all in accordance with NFPA standards.

Control Unit Wiring & Final Testing
The control panel was connected and tested to ensure correct activation from both fusible link melt and manual pull. We conducted a pressure test and simulated activation to confirm proper discharge paths.
Client Briefing & System Training
We walked the client through the full system operation, maintenance reminders, and how to activate/disarm the system safely. Emergency procedures were also discussed.

Make a Comment

Your email adress will not be published. Required field are marked

Prev
Next
Drag
Map
Select the fields to be shown. Others will be hidden. Drag and drop to rearrange the order.
  • Image
  • SKU
  • Rating
  • Price
  • Stock
  • Availability
  • Add to cart
  • Description
  • Content
  • Weight
  • Dimensions
  • Additional information
Click outside to hide the comparison bar
Compare